/Passle/MediaLibrary/Images/2026-01-09-17-39-33-804-69613d551e42b4e613742f47.jpg)
A practical guide to ending contracts early: Frustration (Part 1)
8 minute read
It is a fundamental principle of English law that contracts have binding force. English law is a popular choice of governing law for contracts because of the certainty it provides in ensuring that obligations freely entered into will be upheld, or an appropriate remedy will be granted for their breach – save for in exceptional circumstances.
Driven by recent geopolitical events, we have seen an increase in parties seeking ways to avoid unfavourable contractual terms, or end contracts entirely, without the express right to do so. In this three-part series, we highlight some of the key ways in which parties attempt to do this and examine the current status of English law in each area.
In Part One, we cover the law of frustration.
What is frustration?
Frustration is a common law doctrine which brings a contract to an end if an unforeseen event occurs outside of the control of the contracting parties, and either:
makes the contract impossible to continue to perform; or
transforms the obligation to perform into something so radically different from what was contractually agreed that it has become, in effect, a completely different obligation.
To determine whether a contract has been frustrated, one must first identify what the parties’ contractual obligations are, as a matter of construction of the contract. The next step is to assess what the impact of the alleged frustrating event is on those obligations including how, if at all, the parties can perform those obligations in the new circumstances. The final question is whether the obligation as intended under the contract, and the obligation as it will be performed now, are fundamentally different. As the House of Lords put it, “the question is whether the contract which [the parties] did make is, on its true construction, wide enough to apply to the new situation: if it is not, then it is at an end.”1
Key to the doctrine is that the frustrating event must not have been contemplated (or foreseeable as a serious possibility) and must be outside the control of any of the contracting parties. Self-induced frustration (i.e. where a party’s own acts render its further performance impossible) will not terminate a contract. As discussed further below, foreseeability and control are often where assertions of frustration fail.
What is the effect of frustration at common law?
A frustrated contract is automatically discharged, and the parties are relieved of all future obligations. In effect, from the date of frustration, the contract is terminated. Technically, this does not require either party to make a choice or take an action (subject to any specific terms in the contract). In practice, however, the party who believes the contract to be frustrated will often need to notify the counterparty that this is the basis on which they are (not) proceeding.
Frustration does not mean the contract never existed, and the parties will not be restored to their pre-contractual positions. Any obligations or liabilities incurred prior to the frustrating event must still be fulfilled (unless those obligations or liabilities were frustrated themselves).
Perhaps most significantly, damages are not available for breaches of frustrated contracts after the frustrating event because neither party is considered to be in default. Generally, the approach the courts take to a frustrated contract is that each of the parties must bear their own losses – the party paying for a service, for example, would therefore only pay for the service that has been performed up to the point of frustration.
This position is subject to both statute (see below) and case law2 which provides that if there is a total failure of consideration (i.e. no service under the contract is ever performed), then the party paying for the service may be able to recover any money paid in advance. However, if the services have been even partially performed, then any money paid in advance may not be recoverable, subject to the Law Reform (Frustrated Contracts) Act 1943 (see indent).
The impact of the Law Reform (Frustrated Contracts) Act 1943 (LRA)
The LRA applies to any English law contract which has become impossible to perform provided the contract does not specifically exclude it.
Where the LRA applies, s.1(2) provides that:
any money already paid before the frustrating event may be recoverable. Any money due but not paid before the frustrating event will not be payable; and
a party who has incurred expenses in performing the contract up to the point of frustration may be able to recover those expenses, although this is entirely at the court’s discretion. If ordered, this recovery can either be deducted from money already paid to date, or claimed from the party receiving the benefit of the contract.
Under s.1(3), the court can similarly order a party to pay a reasonable sum for the receipt of any “valuable benefit” at the time of the frustration. This is particularly important as it ensures that a service-provider can reclaim something for services already provided in certain circumstances, although again, this is at the court’s discretion.
Difficulties with establishing frustration
We have seen an increase in parties alleging frustration, seemingly driven by geopolitical events. Clearly, these are events beyond the control of most contracting parties and could potentially frustrate a contract.
However, whether a particular contract has been frustrated will depend to a great extent on the terms and wider context of that contract. The bar for establishing that there has been a frustrating event is high.
The following recent cases illustrate some of the difficulties with alleging frustration.
If the parties appear to have anticipated and provided for what would happen in the frustrating circumstances that have ultimately arisen (or equivalent circumstances), the contract is not frustrated
Salam Air SAOC v Latam Airlines Groups SA [2020] EWHC 2414 (Comm) – the court held that the Covid-19 pandemic was not a frustrating event for an aircraft lease. The lessee had agreed to pay the lease of various aircraft even if the aircraft were destroyed. Thus, even though the pandemic grounded flights, the fact that the lessee had specifically agreed to continue to pay for their lease in a similar (although not equivalent) situation where flights would be impossible suggested that such an event may have been in contemplation of the parties at the time the contract was entered into.
Performance becoming slower, more difficult or more expensive than originally anticipated will not frustrate a contract
Barclays Bank PLC v VEB.RF [2024] EWHC 1074 (Comm) – the court concluded that sanctions did not impede the defendant’s access to justice in the context of an arbitration agreement. The Russian defendant argued that the performance of the arbitration clause under the agreement (whereby any dispute was to be resolved via arbitration in England) was radically different given the effect of sanctions (including arguing it would be difficult to obtain legal representation or for witnesses to attend any hearings in England). The court found this not to be the case as, although there may be delays, it would nevertheless still be possible to arbitrate.
Foreign law illegality is not a frustrating event under English law
Canary Wharf (BP4) T1 Ltd v European Medicines Agency [2019] EWHC 355 (Ch) – the lessee’s incapacity (or potential incapacity) as a matter of EU law to continue to hold an English law lease of premises in Canary Wharf was not a frustrating event. The UK’s (then anticipated) departure from the EU did not make it impossible to perform the lease, notwithstanding that the lessee was an EU entity that would no longer be able to operate from the UK if and when the UK did leave the EU.
It is also important to note that commercial decisions regarding the deployment of resources to satisfy one contractual obligation over another will not amount to frustrating events, even if the underlying circumstances are not the fault of the party alleging frustration. This is demonstrated in Maritime National Fish Ltd v Ocean Trawlers Ltd [1935] A.C., where the Privy Council considered whether a contract was frustrated because a fishing trawler had not been adequately licensed. The owner of the trawler had only been granted licenses by the government for three of its five vessels. The court held that this was not a frustrating event, because although the provision of licenses was outside of the owner’s control, it had made the commercial decision not to apply one of its three licences to the relevant trawler. It was the manner in which the owner had chosen to conduct its business which had caused the trawler to be unlicensed, and that was clearly something within the owner’s control. Although there may have been logical reasons for its decisions, the owner could not rely on the absence of a licence as a frustrating event.
Alternative performance
A contract will not be frustrated if it provides for alternative ways in which it can be performed when faced with what may otherwise be a frustrating event, provided such performance is not radically different from that originally contemplated. For example, clauses which oblige the parties to perform insofar as reasonably possible, or which oblige them to take alternative or additional steps to achieve performance, may prevent a contract being frustrated.
Similarly, before giving notice of a frustrating event, parties should be aware of any other obligations that they may have under the contract to try to overcome the impact of a frustrating event. For example, if a party was contractually obliged to enter discussions with the other party to try to determine an alternative solution, then the court would expect to see evidence of these discussions before accepting that frustration has occurred.
Interaction with force majeure clauses
Analysis of whether a contract has been frustrated often also involves consideration of whether a contract’s force majeure provisions have been engaged, and it is important to understand the key differences between the two concepts.
Force majeure clauses release parties from liability or obligation under a contract when a specified event or circumstance beyond their control occurs. Although the events specified are generally extraordinary and/or unexpected, they are specified in the contract itself. That means that they are not unforeseen by the parties, which means they generally cannot be relied on as frustrating events.
While frustration results in automatic discharge of the contract, the result of a force majeure event must be specified in the contract. Therefore a force majeure event may not necessarily result in termination. Generally, force majeure clauses are easier to invoke than frustration, but this is only a relative measure: disputes over the engagement (or not) of a force majeure clause are common.
In the next part of this series, we will consider the common law doctrine of termination for repudiatory breach.
Authors
Related topics
Like what you are reading?
Stay up to date with our latest insights, events and updates – direct to your inbox.
How can we help you?
Browse our people by name, team or area of focus to find the expert that you need.